Project: XYZ Business Workflow Expected Start Date: March 1st Expected End Date: December 15th

Full-time r esources:  Software architect—Michael Lee

 Technical team lead—To be decided (TBD)

 Software developers—TBD

 Software testers—TBD  UI design and development team—TBD

Part-time r esources:  Julia Smith—Product Manager (ABC Workflow v3.0)

 Ryan Hernandez—Team Lead (ABC Workflow v3.0)

Effort Estimates:

Task Estimated efforts

(workweeks)

Requirements Analysis 1 UI design and development 3

Feature 1 Development 10 Feature 2 Development 8

Feature 3 Development 7 Feature Customization 1 6 Feature Customization 2 6

Feature Customization 3 4 Feature Customization 4 3

Feature Customization 5 1 Software System Testing 1

  • QSO 340 XYZ Business Workflow Resource and Effort Estimates
    • Full-time resources:
    • Part-time resources:
    • Effort Estimates:

Get Top-Notch Quality Essays TODAY !

Ready to join our block community of business leaders for four days of virtual sessions on driving developer happiness and boosting productivity?

Place Order